There was a wooden bridge across the Vltava as early as the 10th century,
slightly north of the spot where Charles Bridge stands today. It was in
essence a foot-bridge and was unable to withstand strong flooding in 1157.
King Vladislav II had Prague's first stone bridge built in the years 1160
to 1172. His wife had urged him to build the bridge and it was given her
name, Judith. It was around 514 metres long, seven metres wide at its
broadest and had 27 low arches. In 1253 administration of the bridge was
taken over by the Knights of the Cross. Two thirds of the structure was
destroyed by a flood in February 1342, necessitating the building of a
replacement - Charles Bridge.
The remains of some of the arches of the Judith Bridge can today be seen
in the basements of buildings, while the foundations of some pillars are
still at the bottom of the river. The smaller of the towers on the Mala
Strana side of Charles Bridge was also part of the bridge's predecessor. A
sculpture of a bearded man in the wall of today's Charles Bridge is said to
be a portrait of the builder of the Judith Bridge, and serves as a measure
of the water level in the Vltava. One of the Judith Bridge's towers is
part of a former monastery which today houses a museum dedicated to
Charles Bridge.
Charles Bridge features three bends and is slightly convex against the
current. While the bridge stands on a stone substratum, its pillars were
built on oak piles loaded with millstones. A probe at the end of the 19th
century found that the millstones are held together by iron clamps on
which hot lead was poured.
The edges of the pillars are visibly more
pointed on the side facing the current and their resistance has been
increased with the addition of wooden ice-breakers. The road in the centre
of the bridge is raised and rain water runs off above the ridges of the
arches by means of stone drains. Rough grained sand was used while large
blocks were held together by unusually firm mortar. Legend has it that
eggs were added to the mortar mix.
The first builder was Master Otto. Around 1360 Peter Parler, Charles IV's
favourite builder and architect, became involved and worked on the bridge
until his death in 1397.
Just ten years after work began, in 1367, one of the pillars of the
as-yet-uncompleted structure was destroyed by flooding. Several times
before it was finished, Charles Bridge was threatened by floods (1359,
1367, 1370, etc.) which caused great damage. In 1432 during floods which
also affected much of the Old Town the bridge was ruptured at three points
and five of its pillars badly damaged. Repairs took an incredible 71 years.
New piles were hammered into the river bottom by means of a hand pile
More harm befell Charles Bridge in 1784 when pieces of broken rafts and
ice blocked the arches and the water carried away pillars on which
military guards were standing. A similar situation occurred in 1890, when
wooden poles from smashed rafts crashed into the pillars. One by one the
fifth, sixth and seventh (counting from the Mala Strana side) arches gave
way. A new method of construction was used during subsequent repairs, when
the pillars were laid on iron cofferdams. This method was gradually used to
reinforce the remaining pillars. The most recent general repair was carried
out in the years 1965 to 1978. Damaged sandstone slabs were removed, while
an asphalt surface from the 1920s was replaced by split blocks of granite.
Since around 2001 plans have been in place to overhaul the upper part of
the bridge and its arches.
|